Can you show me how to have ordinal months instead of ordinal days? maybe using a working calendar 5/7 with fry and sat as a nonworking days? Thx
@PlannersPlace
2 ай бұрын
Use the Excel method and divide by 30 to get a month and them import back into P6 unfortunately, I don't know how to use 5-day calendar for this.
@thsr3283
7 ай бұрын
Hi Sir ... Similar like this, oftentimes we also need to show the week number start & finish instead dates in P6, like example 1 August 2023 is week #1 , 8 August 2023 must be week #2 and so on....What is the formula should be typed in the Global change ? Thanks....
@PlannersPlace
7 ай бұрын
It's easier using the Excel method, because you can account for remainders when dividing by 7 to get week number. It is still possible with Global Change but will require 4 Global Changes instead of 2. Let me know if you still want the Global Change solution and I'll post it on my blog before the end of the month as I'm currently on vacation.
@thsr3283
7 ай бұрын
Yes I am using Excel before export it back into P6, however definitely using Global change is more effective and efficient rather than excel. Thanks if you could teach us your magic. Have a nice vacation Sir....
@PlannersPlace
7 ай бұрын
I've posted screenshots in a blog post www.plannersplace.com/blog/display-number-of-weeks-from-project-start-date-instead-of-dates. I'll try produce a video within the next 2 weeks.
@maqsoodsial1581
2 жыл бұрын
Hi sir, can you make a video that how we can find Late start and late finish dates and how to show them in ordinal days? I will wait for your responce.
@PlannersPlace
2 жыл бұрын
I'll look into this and try and produce it this December