Hi Christian, this comment may not have anything to do with the content of the video posted. However, I was curious if you may know a way to keep the ms project from shifting the summary structure by the earliest date. For example, If in my WBS structure I wanted to keep a summary of milestones at the top of my schedule regardless of what the date of the earliest milestone/task is in that summary, how would I get it to stay at the top?
@vision6D
2 жыл бұрын
Thank you for your question. May be you can find a solution with the milestones report: kzitem.info/news/bejne/uq2d151jnJ6UdGk Greetings from Geneva.