BMA required the relocation (walk) of their P&H 4100XPC Shovel (SHE36), from the North Arm of Peak Downs Mine to the Southern Arm of Peak Downs Mine Via the Peak Downs Mine Road.
BMA commissioned AE Group as Principal Contractor to facilitate this walk. To complete the walk, SHE36 traversed an existing (live) railway line and (live) current main road. To safely facilitate crossing the rail line and road, a temporary bridge was constructed.
In addition to project management, Our team delivered all associated earthworks, abutments, blockwork columns and Lampson Matting Girders / platforming installation for road crossing.
Through strategic planning and proactive coordination between multiple contractors and stakeholders,
we all achieved success.