The first BOXBAY system is now largely assembled. All civil engineering tasks have even been completed. We are currently in the middle of the commissioning phase of the individual systems, which is progressing well. Storage and retrieval machines and the pallet circulation system are working well together. Containers are properly stored/retrieved and transferred to the pallet circulation system, which transports them on and returns them without any problems. The automation software tests also work out very well. The integration of the water-side and landside interfaces has just begun. Based on the current status and the expected progress, the official long-term overall system- and the reliability test program will start soon.