FLSmidth Conveyor System for Sahakol Equipment Public Company Limited’s Mae Moh Overburden Removal Phase 8 project. Largest conveyor in Thailand.
Conveyor System Data:
12 Conveyors Belt Width 2200 mm and 2600 mm.
Capacity 27.600 t/h.
12.6 km length.
Drop -120 m, Lift +310 m.
40 Conveyor Drives 1750 kW and 2000 kW.
Total Weight 10.000 tons.
Total installed power 72 MW.
105 km Cables. 1000 Field Devices. 9000 PLC Inputs and Outputs.
Milestones:
Sahakol-FLSmidth Contract Signing: 18 November 2016
Start of Operation: 1 March 2018
Restart of Operation: 21 June 018 after landslide.
Hand Over Ceremony: 2 August 2018
Project Manager: Helmut Oberrisser, FLSmidth
Video by Helmut Oberrisser