The video shows the first part of the construction of the wall between the garage and the apartment. In the bathroom, I had to pour the foundation before building the wall. In this place, I have already installed the water pipes and the drain for the sink in the wall. The wall itself is made of hollow concrete blocks that are dry-stacked together, after which they are filled with concrete. This process will need to be repeated three times as the wall is too high to be done in one step.