Being able to spot correct near-critical activities of the project schedule is as important as managing critical activities. Hope this video will help you learn the correct way of finding near-critical activities.
@Hasshirkhanbri
11 ай бұрын
Thanks for this video. dear i've a query. if a project is in -90days of total float and total activates are more then 1000, then there will be many activates which causes -ve float of project. 1st: how can i get the total list of activities which causes -ve float? 2nd: how can i get the major activity out of 1000 which cause -ve float.
@krishnachiddarwar505
11 ай бұрын
Answer to first question: there is a simple filter which will give you the list of activities with negative float. Second Answer: sorting out the activities will give you the tasks with maximum float. More sophisticated way to do it is create alternate float lines
@munkhbatnagdalsuren5238
Ай бұрын
Hello, really appreciated to your video, but in my p6 program my float path column is blank. what should i do?
@shahjalal2946
11 ай бұрын
Make a video on concurrent delay
@sayyedalkhamash9502
2 жыл бұрын
i have critical activites i want to make them non critical how
@krishnachiddarwar505
2 жыл бұрын
Sorry Sayed, it does not work that way. On paper you do things which add float to your activities make something else critical 😄😄
@munawarjack91
3 жыл бұрын
Hi Sir i m watch ur p6 videos to learn p6 my request you to prepare advance tutorial as well most important Recovery/ Revised/EOT/ Mitigation/ Contingency... Etc Schedule asap
@krishnachiddarwar505
3 жыл бұрын
Thanks for watching and your suggestions, will try to make videos on your suggested topics as well!!