Bay Terminal Breakwater project. Chittagong. Bangladesh
Bay Terminal Breakwater project site. With Singapore team.
Introduction and Background
Chittagong Port Authority is the managing authority for Chittagong Port which is the principal seaport of Bangladesh handling about 92% of import-export trade of the country. As such its importance in the national economy is paramount. Its objective focuses mainly on providing necessary services and facilities to the port users efficiently and effectively at a competitive price. It provides a major gateway for the country's trade with the outside world. To meet the challenges of globalization and liberalization of world trade and economy, Chittagong Port has undertaken many ambitious projects to enhance its capacity, improve efficiency and quality of services and also to develop adequate Facilities to turn itself into a world class regional port.
To allow further expansion of the Chittagong port, Bangladesh plans to build a new terminal outside of the Karnaphuliriver. The terminal is already partially protected by a large sandbank/island running parallel offshore to the planned terminal.
OBJECTIVE
The objective of the proposed work is to carry out Bathymetric, Geophysical Surveys and Geotechnical survey INVESTIGATION AT Chittagong Bay Terminal Breakwater, Chittagong, Bangladeshfor the following purpose, Detailed Engineering Design of Breakwater for Bay Terminal and Assess the Actual Volume of Capital Dredging Including Necessary Studies of Access Channel.
The scope of services shall comprise all the field investigation studies necessary to plan and develop a suitable layout and design for the Chittagong Bay Terminal Breakwater (the development).
SURVEY AREAS AND SPECIFIC REQUIREMENTS
Single Beam Bathymetry: Approx.53 40 sqkm
in water depth from about 2 to 13 m Chart Datum
Multibeam Bathymetry
Single Beam Bathymetry. Line spacing to be 200m: Approx.200 170 sqkm in water depth from about 7 to 15 m Chart Datum
Marine Boreholes in water depth between 0 to 10m Chart Datum
vibracores
ADCP
OBS
Sand traps
Grab samples
Water samples
Water profile
CPT
Soil/water sample tests