Thanks Phil. I'm a PMP but I still come back to refresh myself. You are a gifted teacher.
@pmpexam
7 жыл бұрын
Thanks Cecil. Hope you are enjoying your newfound PMP freedoms :-) Haha!
@khulekanianderson834
Жыл бұрын
This is an excellent presentation, sir. You demystified the technique of EVM and articulated it for anyone to understand it
@askwaleed1
5 жыл бұрын
Simple, straight & efficient....... Thanksssss
@malikfaizanmahmood213
4 жыл бұрын
Thanks sir for sharing. Really helped me for my bachelor's thesis
@billdowpmo_pmcoach
5 жыл бұрын
Excellent Video. Thanks for sharing.
@hrejoice8256
6 жыл бұрын
Thank you for your training and explanation.. Very practical teaching...
@MGBarkell
7 жыл бұрын
Excellent lesson I will take with me to the exam room and beyond. Thank you!
@pmpexam
7 жыл бұрын
Thanks Mike!
@ppsayl1235
5 жыл бұрын
So earned value doesn't become an EV variable until the work that is planned becomes measurable by means of tangible work/time completion (0%-100%) against that planned work, correct?
@ruwanhewavitharana7980
6 жыл бұрын
Very good explanation. Thank you very much.
@ginjupallyvamshi7718
5 жыл бұрын
Splendid video
@pmpexam
2 жыл бұрын
Thank you!
@dearosman1
8 жыл бұрын
thank you Mr Philip I had learned this lesson it's clear more reliable. please keep on going this lessons
@pmpexam
7 жыл бұрын
Thank you Osman!
@angelaphillips2871
6 жыл бұрын
Phil, Does the type of contract effect the Earned Value Management process? For example, will a Cost plus fixed fee contract be managed the same as a T&M contract ?
@NguyenMInh-hf3sl
6 жыл бұрын
Excellent accessing method. Thanks for sharing!
@pmpexam
5 жыл бұрын
Thank you!
@preciousosegi9680
7 жыл бұрын
Thanks a lot Mike. Great job!
@pmpalihena
6 жыл бұрын
Where is the BAC (Budget at Completion)? Don't you need this value for the calculations too?
@santuchatterjee823
2 жыл бұрын
Hi Phil...Can you please make a video on the forecasting technique
@pmpexam
2 жыл бұрын
Hi Santu! Check these videos out: kzitem.info/news/bejne/qZmkqop8q4phhaQ and kzitem.info/news/bejne/1aqDsnynm6eTa3Y Does that help? Cheers!
@Denise-sq4wy
7 жыл бұрын
Hi Phill, I have to implement a simple cost tracking and performance tool for projects. We do have a project plan with activities, but costs are simply tracked against an approved budget and key cost categories. (eg: Plant and equipment = approved budget of US$300K , Hardware = approved budget of US$ 20K etc) Can i still use EVM based on assigned cost categories?
@pmpexam
7 жыл бұрын
User question: Hi Phill, I have to implement a simple cost tracking and performance tool for projects. We do have a project plan with activities, but costs are simply tracked against an approved budget and key cost categories. (eg: Plant and equipment = approved budget of US$300K , Hardware = approved budget of US$ 20K etc) Can i still use EVM based on assigned cost categories?
@pmpexam
7 жыл бұрын
Yes Deni. It depends. You can use Earned Value on this project if you have an approved budget (Baseline) broken out into the time periods that the costs are expected to hit. If you do not have the expected costs (approved budget) broken out by time period, you will be unable to efficiently use SPI but you could still use a weak version of CPI depending on your data. Do you have the approved budget broken out by time period for each activity or cluster of activities (work packages)?
@abdulhamidabozaid3669
8 жыл бұрын
so simple and clear .. thank you .
@pmpexam
8 жыл бұрын
+Abdulhamid Abozaid Thank you!
@aryaardhana6452
7 жыл бұрын
How come the progress values in March could be lower than the previous months? Does it make sense? Does the progress value should be increased on the next following months?
@pmpexam
7 жыл бұрын
Good question Arya. This is looking at the months in isolation (stand-alone) as opposed to cummlatively (adding them up as the months go on). For example EV for Jan = 8 , EV for Feb = 6, EV for March = 3 (stand-alone) OR CUMULATIVE TOTAL EV at end of Jan = 8 TOTAL EV at end of Feb = 14 TOTAL EV at end of March = 17 (cumulative). Does that help?
@VanessaKlinger
8 жыл бұрын
So the project is behind schedule by 90% and we are over budget 86% respectively? Thanks
@pmpexam
8 жыл бұрын
Vanessa - it is the reverse, the project is 10% behind schedule and 14% over budget. You could say you are only making 86 cents for every dollar spent. You are not getting the full value for your money. You can also say you are only 90% efficient schedule-wise and 86% efficient cost-wise. Also, you are spending 10 days working on the project but only achieving 9 days worth of work.
@Welcome2TheInternet
8 жыл бұрын
good video. thanks
@pmpexam
7 жыл бұрын
Thank you Sir!
@queenkize
9 жыл бұрын
Per your video, if I worked and spent only $3,500 from the $5,000 planned value, how come I ended up spending more on the actual cost if I only produced less than I planned for?
@pmpexam
8 жыл бұрын
+queenkize - it was explained at 4:11 Cost overruns due to resource risks and weather delays. On a real project this could be several possible reasons. So in this scenario the PM got less than planned done and the project is late because the originally planned "core team" is unavailable and there are weather challenges.
@spellru23
7 жыл бұрын
The light bulb went on - thank you
@pmpexam
7 жыл бұрын
Awesome! Glad to hear that Ruby! Thanks :)
@allaboutpixhawkandrpi3691
6 жыл бұрын
Awesome Lesson Bro ! learned alot!
@pmpexam
5 жыл бұрын
Thank you Moe!
@3sSSSSSam
9 жыл бұрын
u great
@pmpexam
8 жыл бұрын
+3sSSSSSam Thank you!
@FD-lo8xr
9 жыл бұрын
thank you i needed this :)
@pmpexam
8 жыл бұрын
+fAMOSS DAMOSS Thanks!
@courtneyellis1704
8 жыл бұрын
How did you graph this?
@pmpexam
8 жыл бұрын
@Courtney by entering the values in Excel. Excel has the graph function.
@fernandoenriquez8573
8 жыл бұрын
how did you graph
@pmpexam
8 жыл бұрын
@Fernando by entering the values in Excel.
@fernandoenriquez8573
8 жыл бұрын
Thank you sir for your feedback but perhaps the better question is how to construct a set up using "plug & play"; an instrument that is predetermined in excel, or so it seems.
@pmpexam
7 жыл бұрын
If I understand your question it is by putting in the formulas and letting excel do the calculations and manipulations?
@queenkize
9 жыл бұрын
Hi, I am actually taking the PMP course, is it okay if I could have your email address?
@pmpexam
8 жыл бұрын
+queenkize All the best in your test. Have you taken it? support@praizion.com
Пікірлер: 51