Timeline:
Tore down my beautiful deck beginning of May 2020:
• Tearing Down my Deck i...
Broke ground with earthwork end of May 2020
Poured foundation first week of June 2020
• Foundation for our DRE...
Framing started middle of June (Did it in 6 days and yes we did beat the lumber price spike)
• Home Addition 6 Days F...
Plumbing, Roof, and Siding July 2020
• Siding Installation Ti...
HVAC and Electrical in Aug 2020
Drywall, paint, electrical finishes Sept 2020
• Home Remodel Master Be...
Kitchen flooring and cabinets Oct 2020
Counter tops and kitchen finished Nov. 2020
• Kitchen Remodel! IKEA ...
Family room finishes (Entertainment Center) Dec. 2020
• DIY Built In Entertain...
Trim and Railings Jan. 2021
Lights, backsplash, and all the never ending finishes have been a work in progress throughout spring!
• Dream Lighting that I ...
• How to Install Mosaic ...
Earthwork & Foundation: $18,000
Lumber and Framing: $14,000
Roof: $1,200
Windows and Doors $2,500
Siding: $4500
Electrical: $2,000
Plumbing: $1,000
HVAC: $5,000
Drywall: $8,000
Paint: $600
Flooring: $1,500
Cabinets: $6,800
Counter Tops: $4,000
Trim: $1,200
The remainder is miscellaneous stuff combined with over 100 trips to Home Depot!