I got error after running the 2nd global change function to change Planned & finish dates to start 5D & Finish5D . Some activities got changed but for some other activities it is showing as "Error: Cannot modify "
@bananmd751
5 ай бұрын
we can just do that with one global change by mutipling the original duration by the ratio between the original duration before and after changing the calender.
@miaksozs
6 жыл бұрын
Very good and quick explanation for changing the calendar , I appreciate if you can explain us the loading of non labors cost in P6 in quick way
@dptutorials
6 жыл бұрын
Thanks a lot for the feedback. Will surely cover this topic one day, as I am currently going step by step. I welcome you to subscribe this channel to enjoy more interesting videos.
@miaksozs
6 жыл бұрын
thanks a lot , please i appreciate if you provide me the method of loading the non labor resources
@shiyas155
5 жыл бұрын
thank you very much...my program worked well this way. But after scheduling date got changed little
@anithrocks
2 жыл бұрын
Hi bro.. Got a query ? Will not global Change affect all projects in the system ?? So when i make the final change as 5D start to Planned start, What will happen to other projects in the same data base ?
@dptutorials
2 жыл бұрын
global change will be applied to only the opened project.
@byrn1s0nl0rek
Ай бұрын
I tried this in ver23.12, it seems nothing changed. I create 1 activity date 2024-8-19 to 2024-8-30. Do as video told but date is right but if you set project display as hours. You will see project will less 1 hour at finish. Why?
@byrn1s0nl0rek
Ай бұрын
for finish date not work for planed finish date it worked
@par5nto
3 жыл бұрын
Do I use the same process to go from 7 day durations on a 7 day calendar to 5 day durations on a 5 day calendar?
@nazirahmad4712
2 жыл бұрын
Thank you ustad
@dptutorials
2 жыл бұрын
Most welcome
@jerabraham
3 жыл бұрын
You are a Life Saver
@dptutorials
3 жыл бұрын
Most Welcome
@shirinh1488
Жыл бұрын
How can I change 5*8 calendar to 7*12?
@ahmedabdelfatah92
4 жыл бұрын
please Can u explain how to use 2 difference calender in the same Project ? and how we can keep finish date un changed
@dptutorials
4 жыл бұрын
Please add a column "Calendar" and by activity wise you can select the desired calendar.
@ahmedabdelfatah92
4 жыл бұрын
@@dptutorials I mean that will change finish date but I want how to keep it
@fas-yt765
3 жыл бұрын
I have a doubt sir if we allocate Resource to the activity before doing change.it may have variation in units and cost After changing the calendar.is it
@dptutorials
3 жыл бұрын
Yes.
@fas-yt765
3 жыл бұрын
@@dptutorials how can we rectify the resource change during this method
@PenyebarIslamChannel
3 жыл бұрын
@@fas-yt765 maybe you can export it first the resource to an excel file, after the calendar change, you import it back the unit and cost..