Since the Tasiast mill fire in June 2021, excellent progress has been made re-starting milling operations. The Tasiast mill has re-started at costs lower than original estimates. The mill is now ramping up and is expected to produce approximately 15,000 Au eq. oz. during Q4 2021. Tasiast remains on schedule to reach throughput of 21,000 tonnes per day by the end of Q1 2022. For more information, please visit Kinross.com and read Kinross’ Q3 news release dated November 10, 2021.