The fact that I am new in this field, I spent a month studying your videos, really , I felt self-confident. thanks you very much
@TomStephensontraining
Жыл бұрын
Wonderful I’m glad they are helping you!
@markpfister1347
3 жыл бұрын
I appreciate the videos you have been producing on MS Project. I think yours are the most relatable and easy to understand.
@TomStephensontraining
3 жыл бұрын
Thanks for the kind words
@rethwickramesh3797
Жыл бұрын
I am confident on creating and editing calendars on MS project now. thankyou.
@TomStephensontraining
Жыл бұрын
Great, excellent!!!
@gte225e
11 ай бұрын
I'm so glad I found these!
@TomStephensontraining
11 ай бұрын
Great, I’m glad they help
@karolinaorlinska6995
3 жыл бұрын
Tahanks!! thansks!! I was looking for where use kalendar in Gant. And only you showed me that - thanks. Best regards from Poland
@TomStephensontraining
3 жыл бұрын
Thanks Karolina I’m happy to help!
@youtubevideos4280
Жыл бұрын
Nice info sir..may God bless u
@TomStephensontraining
Жыл бұрын
Thanks so much and same to you!
@alishah5403
2 жыл бұрын
My project has some tasks for which typical day is 8hrs per day and some for which 24 hrs a day - how do i assign each task to their respective schedule? When I select 24 hr vs standard for each task, the 24 hours thinks its 8 hour work day happening 3 times and doesn't give me proper duration - it gives me 1 day duration instead
@TomStephensontraining
2 жыл бұрын
I’ll check it out to see what’s going on. I intend to do a video coming up to answer these types of questions.
@ig7061
9 ай бұрын
Good day Dear tom. I assigned two work resources with different calendars to the same task, but it is not reflected in the indicator column as a special calendar for the task. What can I do for it?
@TomStephensontraining
9 ай бұрын
Yes I would not advise assigning 2 work assignments to the same task where possible split or double the task so you can hold accountable. Also projext wont know which calendar to follow
@nessim.liamani
2 жыл бұрын
Hi Tom, Do you think we can find anywhere on the web, some sort of MS Project Files already populated with diffrent countries calendar? Or maybe there is an option nested in MSP to automatically populate our project with just that? Do you have some info for that? BTW, I'm already Googling it just in case. Thanks.
@TomStephensontraining
2 жыл бұрын
Not that I’m aware, Ill try to do a video on making a template for holidays 10 years out