MULTIPLE FLOAT PATH:
Primavera P6 can compute float paths based on setting by the Users. As we know that that in a Activity network there are several path to finish the project. The path which determines the duration of the project is called CRITICAL PATH and all activities on this path is called CRITICAL ACTIVITIES.
Primavera P6 enables to users to compute float path based on Total and Free floats. For overall Project status, the Total float is used while if we want to know the path for the completion of intermediate activity or milestone Free float will be used.