Speaker information: Pankaj Kumar Jha
Manager, Power Grid Corporation of India Ltd.
(Power System Engineer with more than Ten (10) years of industrial experiences.)
The concept of connection of Main and Tie Bay CTs and the current distribution in One and Half CB Scheme are explained in detail in this video. Why CT star point is always formed towards protected object side??. The concept is explained through use of application example by hand written notes.
For better understanding of this session, please watch the fundamental concept session on CT Star point formation by clicking on the following link:
• CT POLARITY || WHY CT ...
• CT POLARITY || WHY CT ...
Please click on the below link for watching the same video in English.
• PART-1: Current Distri...
You may use the following time stamp to navigate easily:
00:00 - Intro
03:25 - One and Half CB Scheme
06:25 - Connection of Main & Tie CT and formation of Star Point.
12:38 - Current Distribution with all CBs in Closed condition. CT Star Point of Main & Tie CT are correct.
18:47 - Current Distribution with all CBs in Closed condition. CT Star Point of Tie CT is incorrect.
26:01 - Current Distribution with all CBs in Closed condition. CT Star Point of Main & Tie CT are incorrect.
29:35 - Concluding Remarks
We need your support...Why?
An incredible amount of time and effort is needed to develop high-quality video tutorials. Each video takes approximately 6-8 hours to complete which includes learning the concept myself, brainstorming creative ways to teach and explain the concepts, creating the presentations, video recording, and editing. Your support truly makes all the difference. So, Please like👍🏻, comment and share this video with your friends and keep watching this channel for more such videos in future.
#Lightningminds #pankajkumarjha
Негізгі бет PART-1: Current Distribution in One and Half CB Scheme || How to connect Main & Tie CT || Star Point
Пікірлер: 19