Hey, I just wanted to say thank you for making these videos! These videos literally helped me pass my operational management course
@Engineer4Free
5 жыл бұрын
That's awesome!!! Thanks for letting me know =)
@qhakazilenono4471
3 жыл бұрын
Can you please help me am struggling
@Engineer4Free
3 жыл бұрын
Full playlist is here: engineer4free.com/project-management I recommend starting at the beginning and working along! It will be worth your time
@Jasminlieber
10 ай бұрын
Thank you! Those videos are really helpful for me, especially at the first semester of learning project management.
@shahzebchoudry6175
3 жыл бұрын
Very very very very*100 clear and understandable information
@taufeqtauf1817
8 жыл бұрын
All the project management videos are great, thank you
@andilenjani9310
4 жыл бұрын
Amazing thankyou, the day before my Construction Management exam!
@Engineer4Free
4 жыл бұрын
Good luck!! Check out engineer4free.com/project-management for the rest of the videos if you haven’t already!!
@andilenjani9310
4 жыл бұрын
@@Engineer4Free I'm confident in saying I got the crashing Question correct thanks to you! I have also bookmarked your website for the rest of my Civil Engineering ,degree It looks fantastic! Thank you for the great work!
@Engineer4Free
4 жыл бұрын
@@andilenjani9310 Amazing!!! So glad to hear it 😁. Thanks for the bookmark, and please share it with some friends in your classes too 🤜🤛
@chewiearmy5524
Жыл бұрын
I thought I would never get this. Thank you for this video.
@mehdi.sajadi
2 жыл бұрын
you're amazing man , thank you so muuuuuuuuuuuuuuuuuuch
@sevdaeren5370
4 жыл бұрын
For activity A, if the crash duration would be 1, still you won't crash it. Can you please explain why? Why it is a good idea and why it is a bad idea?
@Engineer4Free
4 жыл бұрын
Hey i did a 2 part video solving this exact problem and explaining everything, it's here: kzitem.info/news/bejne/u4WNmIWLmKWTfWk and kzitem.info/news/bejne/kaV4u6yoqayIm4I
@lexparsimoniae2107
7 жыл бұрын
Very clear explanation! Thank you!
@minafathi1164
3 жыл бұрын
thank you so much! helped me alot.
@Engineer4Free
3 жыл бұрын
Glad it helped! You can check out the rest of the playlist here: kzitem.info/door/PLOAuB8dR35oeyKU0ojIxD8Muf6Mwc8ugW =)
@minafathi1164
3 жыл бұрын
@@Engineer4Free Almost finish all videos. Thank you again👍
@jyotinegi7413
2 жыл бұрын
when crashing a project do we have to concentrate on task with least expensive gradient or path with least slack?
@MitulShah114
5 жыл бұрын
What if the fixed cost is not mentioned in the question? Do we assume something?
@Engineer4Free
5 жыл бұрын
If you're not given a fix cost, don't worry and be happy, assume there is none.
@dawnnelson1814
2 жыл бұрын
I cant see the bottom chart layout... too blurry
@carlodelossantoslebron7874
3 жыл бұрын
Hello. Very helpful video. My only question is if it is possible to do partial crashing? For example, I need to reduce the days of a project by 3, but the crash duration of the next cheapest option is 5. How can I calculate the cost for this activity after partial crashing?
@sanamehtab5392
5 жыл бұрын
Can u help me in a question?
@saraair7939
7 жыл бұрын
Thank you so much 🌹
@Engineer4Free
7 жыл бұрын
Thanks for the rose! Glad you liked the video :)
@xzotzvvs6492
8 жыл бұрын
Nice one
@reetikaaggarwal2587
6 жыл бұрын
Hi can you please tell me how to crash an activity if its in critical path and it’s normal time is less than crash time?
@Engineer4Free
6 жыл бұрын
Normal time less than crash time sounds like a typo, I'd ask your professor to make sure it's not.
@Memento-_-Mori-_-982
6 жыл бұрын
E is written as preceded by E&F while it should be D&F!
@Engineer4Free
6 жыл бұрын
Good eye, thanks for pointing it out, I've added your note to the description!
@Pepperrinooo
7 ай бұрын
Shouldnt it be C,D since F would have the predecessor E not vice versa ???
Пікірлер: 34