Singaperumalkoil flyover work shared in this video.
Flyover arm from Sriperumbudur road towards Tambaram direction work completed. Tar laying, Light installation & finishing touch work need t be completed. Hope atleast this flyover arm will be open to public soon.
Elliptical rotary arm work is completed around 40%.. Pillar & girder work in progress. Flyover arm starting from Chengalpattu side towards Sriperumbudur direction 90% work completed. Just around 40 metres girder work need to be complete.
Flyover arm starting from Chennai towards Sriperumbudur direction around 60% work completed.
Flyover arm starting from Sriperumbudur towards Chengalpattu direction work in progress at GST road side. Pillar and down ramp work in progress.
Once elliptical rotary flyover arm work completed this flyover project will be fully completed. I think it will take around 4 to 6 months