Dear Sir I had a problem in Primavera P6, the problem is Performance % Complete and Schedule % Complete, can not roll up to Project level, but it is already rolling up to WBS Level, and please note that I already assign materials on activities. Please anyone can give advice, to solve this problem, I use Ver. 19.12 and Ver. 21.12. Thanks