It is week 21 of the Warm Springs Enhancement Project and things are developing fast around here! The snowmaking line has been buttoned up on Lower Flying Squirrel, and the lift towers are almost all in place for the new Challenger & Flying Squirrel lift lines! Crews continue to make tons of progress at the midstation & top terminal site for new Challenger, and are working to install the operator house & drive platform at the top of new Flying Squirrel lift.
Stay tuned for more weekly updates, and visit www.futureofsunvalley.com to learn more about the project!