Week 12 of main house framing. A long holiday weekend and Jason worked hard to prepare for concrete for our 18’x11’ patio off of our master suite. He dug out the columns, dried out the columns with our new handheld propane torch, measured out and setup the concrete forms, and started adding rebar. Jason also got the wooden base for the columns made. Katie broomed off all of the mud splatter from the exterior sheathing, marked out the height for the Tyvek house wrap and cleaned up the construction debris in the yard.
Jason worked hard over the weekend and a couple of late evenings this week to get the rebar and concrete forms ready for concrete pour day! Jason took vacation time today to knock out the concrete pour with our concrete finishers. We paid $1200 to place and finish the concrete, $2300 for 12.5 cubic yards of concrete, and $250 for the concrete vibrator. A total of $3750 for our 18’x11’ covered patio. 4500 sqft covered in concrete between the foundation and the patios, the last concrete pour for a while until we move onto the pool house and pool.
We received our window order, 60 windows (with an additional 3 on the way plus the mitered windows). Jason worked on plumbing this weekend and installed 200 feet of 3/4” and 1/2” copper pipes in the attic. The water lines supply the master suite and the kitchen. The framers also got the trusses over the 2nd story fixed.
Subscribe to watch Drs. Harke build our dream Bay Area homes from the ground up.
Framing company: CFI Construction - / cficonstruction
#harkeestate #newconstruction #housebuilder #framing #build #construction #builder #homebuild #heavyequipment #heavymachinery