PROJECT DETAILS
Located in Waco, Texas, a new industrial park covering 40+ acres is currently under construction. This project required over 26 acres of area be blasted on an aggressive time schedule. Dykon mobilized a fleet of high production drills and bulk loading equipment to get the job done on schedule. The entire 26 acres of rock area was drilled and shot to completion grade in six weeks.
Visit Dykon Blasting on the web at: