WBS milestone complete seems particularly useful when WBS entirely corresponds Bill of Quantities valued against rules of credit. In this case activities reflect the site works whilst WBS mainly contributes to valuation and financial matters.
@vladimirrisojevic3945
Жыл бұрын
Imposed payment milestones should be applied in P6, on WBS level !? Could You please explain possible relationships between rules of credit and payment milestones!? Thanks
@Pacific998
3 жыл бұрын
i have never used WBS milestone complete..i have not seen it used any schedules at all
@ahmadaltayeb1983
Жыл бұрын
Please Sir, I had a question, why percentages will not roll up to project level in primavera p6, please not that it is roll up in WBS level, and I already assign recourses, please advise.
@omarmdsaleem
3 жыл бұрын
if WBS Milestones percent complete selected, will it change the activities Actuals automatically ?
@kaviwithshanu-pursuitofper9393
2 жыл бұрын
Excellent, I have small clarification, currently I'm working on Master schedule as vendor which contains both contractor and vendor wbs/activities. I update only vendor activities. So when I filter my vendor activities p6 is not summarizing performance %complete. Could you please help to summarize
@kaviwithshanu-pursuitofper9393
2 жыл бұрын
Similar problem, i am also facing. Could you advise if you found out
@benzonjhermogeno
6 ай бұрын
Thanks
@mahansor8295
8 ай бұрын
Hi Michael, I have a resource - cost loaded plan , the performance % is shown zero, I have checked all the settings , could you please advise hoe to resolve the issue . Thank you
@PlanAcademy
8 ай бұрын
Could be a bunch of things. Is it 0% for activities or WBS? Is there progress with values in the "Actuals" fields - Actual Budgeted Cost, Actual Budgeted Units.? I would check those first.
@Aryanss5743
2 жыл бұрын
Dear Sir, When i update the schedule i have performance % values in activities . But in the WBS the performance % is showing as Zero. Please guide me to solve this issue. As i already refresh the schedule many times but still it is showing Zero
@raulrodriguez9892
11 ай бұрын
I am having the same issue? How did you resolve this?
@prasanthk1748
25 күн бұрын
@@raulrodriguez9892 same thing anybody guid me to solve
@he2018xiao-ud2zr
Жыл бұрын
how to make level automatic calculatiom completed
@khaledAhmed-eb4be
Жыл бұрын
0%100% is useful for engineering activities updates , but the problem is settings is qpplied to entire schedule not to certain activity only .
@khaledAhmed-eb4be
Жыл бұрын
Custom also is ok like 75% and 100%
@PlanAcademy
Жыл бұрын
actually, you can apply this to each WBS in P6. So it's applied at the WBS level. Check the WBS screen and tabs for the settings.